Contract Towers:
Observations on FAA’s Study of Expanding the Program
Federal Aviation Administration
Report No. AV-2000-079 April 12, 2000
Background
The Federal Aviation Administration (FAA) began contracting out air traffic services at low activity (Level I) towers in 1982 as a result of the Professional Air Traffic Controllers Organization strike. In 1993, Vice President Gore’s National Performance Review endorsed the Contract Tower Program (Program) as an effective means of reinventing government services. Currently, there are 187 towers in the Contract Tower Program operated by 3 contractors. In July 1999, FAA issued a new solicitation for the Contract Tower Program, but as of April 2000, had not awarded final contracts.
FAA’s Contract Tower Program has been successful in providing air traffic control services at low activity airports at lower costs than the agency could otherwise provide. FAA’s current Contract Tower Program saves the agency about $250,000 per tower, annually. The Program also provides service at towers that FAA would otherwise not have staffed because they were too expensive to operate. In light of the Program’s success, Congress last year directed FAA to conduct a study to determine if additional savings could be achieved by expanding the Contract Tower Program to other FAA-operated air traffic control towers "without radar capability." FAA currently operates 71 visual flight rules (VFR) air traffic control towers employing about 960 controllers. (Exhibit A provides a list of the 71 towers and certain statistical information about each facility.)
Prior Coverage
In 1998 we conducted a comprehensive review of the Contract Tower Program and found little difference in the quality or safety of services provided at Level I towers whether they were operated by FAA or by contractors. Specifically, we found that contract controllers met qualification requirements and received required training, users were satisfied with the services they received at contract locations, and the number and types of incidents at FAA and contract towers were comparable.
We also found that contract towers reduced operating costs. However, we found that not all contract towers were staffed according to contract staffing plans. We recommended that FAA direct contractors to staff contract towers in accordance with contract requirements and establish procedures to periodically review staffing levels at contract towers. Those measures were necessary because contract towers were staffed with fewer controllers than FAA-operated towers and staffing levels were based on contractor-prepared staffing plans.
Objectives
This review was conducted at the request of Congress in the Department of Transportation and Related Agencies Fiscal Year (FY) 2000 Appropriations. The objectives of our review were to (1) determine if contract towers were being staffed in accordance with contract requirements and assess FAA's oversight of contractor compliance, and (2) evaluate the accuracy and completeness of FAA’s study of expanding the Contract Tower Program to determine whether all relevant costs and benefits were appropriately identified and considered. (Exhibit B contains the scope of our review and the methodology used in conducting it.)
Results in Brief
Contract towers continue to provide cost-effective services that are comparable to the quality and safety of FAA-operated towers. For example, the level of operational errors in FY 1999 at contract towers was comparable to the level of operational errors at FAA VFR towers. The Contract Tower Program also provides services at towers that FAA would otherwise not have staffed because they were too expensive to operate. Users remain very supportive of the Program and believe that the services they receive at contract towers are comparable to FAA-operated towers.
We also found that previously reported staffing issues have been addressed. We tested payroll records for a 2-month period at 37 contract towers and found that contractors (in total) provided the required number of employees and hours within 2 percent of the contractual requirements. In addition, FAA’s new contract solicitation contains specific provisions requiring contractors to report and certify monthly the number of controllers at each location and the hours they worked.
FAA completed a draft study of expanding the Contract Tower Program in September 1999, but as of April 2000, had not issued a final report to Congress. In the draft study, FAA concluded that no net savings would be realized from further expanding the Program because of an agreement with the National Air Traffic Controllers Association (NATCA) that establishes a baseline staffing level of 15,000 FAA controllers through 2001. FAA agreed to increase that level by an additional 2 percent each year for the remaining 2 years of the agreement.
While the decision to expand the Contract Tower Program is ultimately a policy determination that Congress will have to weigh, FAA’s study did not adequately consider several key factors of the feasibility, costs, and benefits of expanding the Program that should be further analyzed and reported to Congress.
First. FAA’s methodology for determining which towers to consider did not accurately reflect the feasibility of expanding the Program. For purposes of its study, FAA narrowly defined the congressional request to evaluate FAA towers "without radar capability" and concluded that only 41 of its 71 VFR towers met the definition of Congress. FAA excluded the remaining 30 towers from consideration because those facilities are equipped with a monitoring device known as DBRITE (Digital Bright Radar Indicator Tower Equipment) and provide limited instrument flight rule services (IFR) through a letter of agreement (LOA) with a larger radar-equipped facility. DBRITE is a display monitor used by controllers at towers to identify and monitor aircraft – it is not a radar system and is not used in the radar control of air traffic.
We do not agree that those factors are reasonable causes for including or excluding towers from consideration. For example, there are currently as many as 40 towers in the existing Contract Tower Program that also are equipped with DBRITE displays and provide similar IFR services through LOAs with larger FAA facilities.
In addition, FAA’s methodology went too far in considering some busier towers and not far enough in considering other towers with substantially lower levels of air traffic activity. For example, FAA included Pontiac/Oakland International Airport for consideration (even though this airport is among FAA’s 50 busiest towers) because the facility is not equipped with a DBRITE and does not have an LOA to provide IFR operations. In contrast, FAA excluded Allegheny County Airport from consideration because the facility is equipped with a DBRITE and has an LOA for IFR operations even though this airport has an average air traffic count that is substantially less than many towers in the existing Program. FAA’s experience in contract towers has primarily been with towers that have lower levels of air traffic activity.
FAA needs a more comprehensive means for determining the extent that the Program could be expanded by taking into account factors such as volume of air traffic, types of users, and complexity of operations at each location. As part of its collective bargaining agreement with NATCA in 1998, FAA developed a new pay system for controllers based on reclassifying all its air traffic control (ATC) facilities. The new system establishes ATC Grades 3 through 12 based on the complexity of operations, the types of users, and the volume of air traffic at each location. FAA’s 71 VFR towers were reclassified into ATC Grades 5 through 9.
In our opinion, the ATC Grades of the 71 towers could provide FAA a more comprehensive means for evaluating which facilities to consider. Additionally, should Congress choose to expand the Contract Tower Program, FAA will need to develop specific metrics for analyzing and reporting actual results of the Program’s expansion (on a facility-by-facility basis) to ensure that system safety and efficiency are not impacted and that projected benefits are being fully realized.
Second. FAA’s estimated cost savings were understated because the agency used FY 1998 cost figures. In FY 1999, costs to operate FAA towers increased as a result of the new pay system for FAA controllers. We estimate that annual average savings would be approximately $881,000 per tower. However, these savings would be subject to several offsetting expenses. For example, FAA would incur a one-time expense to relocate FAA controllers who elect to move from contracted facilities to other FAA facilities. According to FAA’s FY 2001 budget submission to Congress, this cost was approximately $49,000 per move in FY 1999 for the Air Traffic Control division.
Third. FAA’s conclusion did not consider important long-term benefits that could accrue from expanding the Program. To have credibility, FAA's study should have given much greater weight to the potential impact that controllers from contracted VFR towers could have in offsetting future increases in system demand and addressing existing staffing shortfalls. Contracting additional VFR tower operations would allow FAA to redistribute controllers from contracted locations (or their equivalent full-time positions) to FAA locations with the greatest forecast increases in air traffic activity. Experienced FAA controllers from contracted locations could also help alleviate existing staffing shortfalls which, in turn, could reduce FAA’s overtime costs.
These benefits would be achievable while maintaining a workforce of 15,000 FAA controllers as specified in the agreement with NATCA. However, it is important to note that the agreement states ". . . its terms and conditions are subject to congressional approval."
It is essential that FAA thoroughly analyze any and all opportunities to offset the rising costs of its operations. Expanding the Contract Tower Program provides the agency with one such opportunity. FAA should revise its study of expanding the Contract Tower Program to fully recognize the feasibility, costs, and benefits that expanding the Program offers. Revisions should include better methodology for determining which towers to consider, new savings estimates, and further evaluation of the benefits that controllers from contracted locations could provide in meeting projected growth in air traffic activity.
Principal Findings
The Current Contract Tower Program
Safety. As part of our review, we conducted tests on issues similar to those we identified in our 1998 report on the Contract Tower Program. We found that contract towers continue to be operated as safely as FAA-operated towers. For example, we found that the level of operational errors in FY 1999 at contract towers (.05 errors per 100,000 operations) was similar to the level of operational errors at comparable FAA VFR towers (.06 errors per 100,000 operations). In addition, we reviewed facility evaluation reports conducted by FAA’s Evaluations Branch for a sample of 34 contract towers and found that none of the evaluations noted any significant safety issues at the contract towers.
Staffing. We also conducted a follow-up review of staffing issues noted in our 1998 report. We reviewed contractor payroll records for a sample of approximately 4 biweekly pay periods (2 months) in 1999 for 37 contract towers and compared the number of employees and hours provided by the contractors to the staffing requirements contained in their respective contracts. We found that contractors (in total) provided the required number of employees and hours within 2 percent of the contractual requirements.
In addition, we found that FAA’s new contract solicitation contains specific provisions requiring contractors to report and certify monthly the number of controllers at each location and the hours they worked. These procedures should help ensure that contractors adhere to required facility-staffing plans under the new contract.
Users. Lastly, we discussed the Contract Tower Program and its proposed expansion with users at contract locations and at proposed locations. Users at contract locations continue to be supportive of the Contract Tower Program and believe the services they receive are comparable to FAA-operated towers. Based on their experiences with the Contract Tower Program, these users felt that expanding the Program to other FAA VFR towers would be feasible. At proposed locations, most users were concerned only that the level of service they receive would remain the same if their towers were converted to contract operations.
However, other users were strictly opposed to expanding the Program. For example, one airport director told us that he used the fact that his tower was operated by the FAA as a marketing tool to attract foreign air carriers and encourage commercial service. Other groups, such as NATCA, oppose expanding the Program for other reasons. NATCA believes that expanding the Program to busier FAA VFR towers would represent a serious departure from confines of the existing Program because the number and complexity of operations at FAA’s 71 VFR towers are significantly higher than operations at current contract towers.
While 15 of FAA’s 71 VFR towers are busier than towers in the existing Program, the remaining 56 VFR towers have, in our opinion, operations that are comparable to towers in the existing Program. These differences underscore the complexities involved in evaluating the feasibility of expanding the Contract Tower Program. They also underscore the need for FAA to develop specific metrics for analyzing actual results of the Program’s expansion to ensure that system safety and efficiency are not affected.
FAA’s Study of Expanding the Contract Tower Program
FAA completed a draft study of expanding the Contract Tower Program in September 1999, but as of April 2000, had not issued a final report to Congress. In its study, FAA concluded that no savings would be realized from expanding the Program because of an agreement with NATCA that establishes a baseline staffing level of 15,000 FAA controllers. However, FAA’s study did not adequately consider several key factors of the feasibility, costs, and benefits of expanding the Program that should be further analyzed and reported to Congress. These include developing better methodology for considering which towers to convert, and evaluating additional cost savings and other benefits that expanding the Program could offer.
Methodology. FAA narrowly defined the congressional request to evaluate FAA towers "without radar capability" and included only 41 of its 71 VFR towers in its study. FAA concluded that the remaining 30 towers did not meet the definition of Congress because those facilities are equipped with a monitoring device known as DBRITE and provide limited IFR services through an LOA with a larger radar-equipped facility. We do not agree that those factors are reasonable causes for including or excluding towers from consideration. For example, there are currently as many as 40 towers in the existing Contract Tower Program that also are equipped with DBRITE displays and provide similar IFR services through LOAs with larger FAA facilities.
In addition, FAA’s methodology went too far in considering some busier towers and not far enough in considering other towers with substantially lower levels of air traffic activity. For example, FAA included Pontiac/Oakland International Airport for consideration (even though this airport is among FAA’s 50 busiest towers) because the facility is not equipped with a DBRITE and does not have an LOA for IFR operations. In contrast, FAA excluded Allegheny County Airport from consideration because the facility is equipped with a DBRITE and has an LOA for IFR operations even though this airport has an average air traffic count of only about 28 aircraft per hour (less than many towers in the existing Program).
In 1998, FAA reclassified all its air traffic control facilities into ATC Grades 3 through 12 based on numerous factors including the complexity of operations, types of users, and the volume of air traffic handled at each location. For example, under FAA’s old grade structure, Chicago O’Hare and JFK International were both classified as Level V facilities but in 1998 were reclassified as ATC Grades 12 and 10, respectively.
Although FAA’s 71 VFR towers were reclassified into ATC Grades 5 through 9, FAA did not use ATC Grades to determine which facilities to include in its study. As a result, FAA did not consider important differences about the 71 VFR towers such as the volume of air traffic they control, the types of users they serve, and complexity of operations they manage. For example, the average hourly traffic density at the 71 towers ranges from 28 aircraft per hour to over 118 aircraft per hour – 11 of the 71 towers are among FAA’s 50 busiest towers. One tower, Van Nuys, California, (an ATC Grade 9) is the fifth busiest air traffic control tower in the country – busier than towers such as Miami International, Detroit Metropolitan, and Boston Logan.
In our opinion, the ATC Grades of the 71 towers offer Congress and FAA a more comprehensive means for evaluating which facilities to consider by taking into account factors such as the volume of air traffic, the types of users, and the complexity of operations at each location. Additionally, should Congress choose to expand the Contract Tower Program, FAA will need to develop specific metrics for analyzing and reporting actual results of the Program’s expansion (on a facility-by-facility basis) to ensure that system safety and efficiency are not affected and that projected benefits are being fully realized.
Estimated Savings. FAA estimated that the agency would realize average annual savings of about $787,000 per facility by expanding the Program. FAA’s estimate was based on a framework using Office of Management and Budget Circular A-76 requirements for cost comparisons. We tested the costs used in FAA’s estimate and found that the underlying data were reasonable. However, FAA’s estimates were developed using FY 1998 costs. In FY 1999, the costs of operating FAA towers increased as a result of the new pay system for FAA controllers.
Using FAA’s methodology and actual contract and agency costs for FY 1999, we estimate that annual average savings could be approximately $881,000 per tower. (Exhibit C provides details of these estimates.) These savings would be subject to several offsetting expenses, however. For example, FAA would incur a one-time expense to relocate FAA controllers who elect to move from contracted facilities to other FAA facilities. According to FAA’s FY 2001 budget submission to Congress, this cost was approximately $49,000 per move in FY 1999 for the Air Traffic Control division.
FAA’s Conclusions. In its study, FAA concluded that no savings could be realized from expanding the Contract Tower Program because of a July 1998 Memorandum of Agreement between FAA and NATCA. Article I of that agreement establishes a baseline staffing level of 15,000 controllers for FYs 1999 through 2001, increasing by an additional 2 percent each year for the remaining 2 years of the agreement. FAA agreed to maintain those numbers when attrition, transfers, or promotions reduced those levels. As a result of those requirements, FAA concluded there could be no net savings from expanding the Program because the agreement prohibits a decrease in the number of FAA personnel.
FAA’s conclusion is based on a premise that there could be no savings from expanding the Contract Tower Program because the agency would have to increase the costs of the Program while maintaining the same level of FAA controllers. However, FAA’s conclusion ignores other long-term benefits that would accrue from expanding the Program. For example, controllers from contracted towers could have a significant impact in meeting projected increases in air traffic demand. As shown in the following graph, FAA is forecasting aircraft operations at airports with FAA-operated air traffic services to increase from about 54 million in 2000 to over 67 million in 2010 – an increase of over 24 percent.
Forecast Aircraft Operations at Airports with FAA-Operated Air Traffic Services
FAA's study should have given greater merit to the potential impact that controllers from contracted VFR towers could have in offsetting potential future increases in system demands. Contracting out additional VFR tower operations would allow the agency to redistribute controllers (or their equivalent full-time positions) from contract locations to FAA locations with the greatest forecast increases.
Experienced controllers from the 71 facilities would also reduce FAA’s projected hiring needs thus reducing costs associated with training newly hired controllers. FAA spends approximately $47,000 per employee to provide newly hired controllers initial air traffic control training. According to FAA officials, the agency is projecting to hire approximately 2,000 new controllers over the next 4 years.
In addition, experienced FAA controllers from contracted locations could help alleviate existing staffing deficiencies. For example, as of December 1999, the Los Angeles International Airport tower was understaffed by eight controllers. If the Program were expanded, the 13 controllers assigned to the Santa Monica tower (or their equivalent full-time positions) could be reassigned to Los Angeles International to address that facility’s staffing needs. Actions such as these would also help FAA reduce overtime expenditures at understaffed facilities. In FY 1999, FAA incurred over $19 million in overtime costs to meet operational needs at its air traffic control facilities.
FAA should more carefully examine the potential benefits that expanding the Contract Tower Program could provide in addressing staffing deficiencies and ensuring that FAA has sufficient resources at key locations to meet projected increases in air traffic activity.
Recommendations
We recommend that FAA revise its draft study of expanding the Contract Tower Program to provide Congress a better perspective of the feasibility, costs, and benefits of expanding the Program. Revisions to the study should, at a minimum, include:
Additionally, should Congress choose to expand the Contract Tower Program, we recommend that FAA develop specific metrics for analyzing and reporting actual results of the Program’s expansion (on a facility-by-facility basis) to ensure that system safety and efficiency are not impacted and that projected benefits are being fully realized.
TABLE OF CONTENTS
TRANSMITTAL MEMORANDUM
EXECUTIVE SUMMARY
FINDINGS AND RECOMMENDATIONS
The Current Contract Tower Program 1
FAA’s Study of Expanding the Contract Tower Program 4
Recommendations 10
EXHIBITS
Exhibit A. 71 VFR Towers Considered in FAA’s Report
to Congress on the Contract Tower Program 11
Exhibit B. Scope and Methodology 13
Exhibit C. Comparison of Potential Cost Savings for
FY 1998 and FY 1999 14
Exhibit D. Activities Visited or Contacted 15
Findings and Recommendations
The Current Contract Tower Program
The Federal Aviation Administration’s (FAA) Contract Tower Program (Program) has proven successful in providing air traffic control services at low activity airports at lower costs than the agency could otherwise provide. The Program also provides service at towers that FAA would otherwise not have staffed because they were too expensive to operate. According to FAA, significant cost savings have been achieved, air traffic services have been maintained without derogating safety, and the quality of service to the customer has been maintained at a high level. In its study of expanding the Contract Tower Program, FAA states:
Services provided at a [contract tower] are identical to those provided at an FAA-staffed [tower]. Contract air traffic controllers are certified by FAA and must follow appropriate Code of Federal Regulations and FAA directives. The change to contractor-provided air traffic control services is transparent to users.
In 1998, we conducted a comprehensive review of the Contract Tower Program and came to many of the same conclusions as FAA. We found little difference in the quality or safety of services provided at Level I towers whether they were operated by FAA or by contractors. Specifically, we found that (1) contract controllers met qualification requirements; (2) contract controllers received required training; (3) users were satisfied with contract tower services; and (4) the number and types of incidents at FAA and contract towers were comparable.
We also found that the Contract Tower Program reduced FAA’s operations costs. The current Contract Tower Program saves the agency about $250,000 per tower, annually. However, we found that some contract towers were not staffed in accordance with contract terms.
We recommended that FAA closely monitor contract tower staffing levels. This was necessary because (1) contract towers are staffed with fewer controllers than FAA-operated towers, and (2) staffing levels were based on contractor-prepared staffing plans. FAA agreed to those plans because the agency does not have precise standards for estimating staffing requirements for individual facilities.
As part of our current review, we conducted tests similar to those we did in 1998. Specifically, we wanted to determine (1) if the Program continues to operate safely, (2) if previously identified staffing issues have been addressed, and (3) if users continue to be satisfied with the Program.
Safety. Contract towers continue to be operated as safely as FAA-operated towers. For example, we found that the level of operational errors and deviations in Fiscal Year (FY) 1999 at contract towers (.05 per 100,000 operations) was similar to the level of incidents at a sample of comparable FAA visual flight rules (VFR) towers (.06 per 100,000 operations).
In addition, we reviewed a sample of facility evaluation reports conducted by FAA’s Evaluations Branch for contract towers. The Evaluations Branch conducts extensive biennial full-facility reviews of all air traffic facilities. Our sample included the most recent evaluations conducted at 34 contract towers. None of the evaluations we reviewed noted any significant safety issues at the contract towers.
Staffing. We also conducted a follow-up review of staffing issues noted in our 1998 audit. We reviewed contractor payroll records for a sample of approximately 4 biweekly pay periods (2 months) in 1999 for 37 contract towers. We then compared the number of employees and hours provided by the contractors to the staffing requirements contained in their respective contracts. As shown in the following table, we found that contractors (in total) provided the required number of employees and hours within 2 percent of the contractual requirements.
STAFFING SAMPLE RESULTS BY CONTRACTOR
Controllers* |
Hours per Pay Period |
||||||
Company |
Pay Records |
Contract Terms |
Difference |
Pay Records |
Contract Terms |
Difference |
% |
1 |
268 |
268 |
0 |
19,868 |
20,220 |
(352) |
(2)% |
2 |
196 |
190 |
6 |
13,737 |
13,664 |
73 |
1% |
3 |
300 |
300 |
0 |
21,304 |
21,492 |
(188) |
(1)% |
*These figures represent the total number of controller pay records for 4 biweekly pay periods in our sample. They do not reflect the actual number of controllers employed at the towers reviewed.
FAA has also specifically addressed facility-staffing variances in its new contract solicitation. The new contract contains three provisions addressing staffing issues that should strengthen the agency’s oversight of the Contract Tower Program. First, the new contract requires the contractor to submit a monthly report to the FAA Contract Tower Program Office including such items as total hours worked and the number of facility-rated controllers working each month.
Second, the new contract addresses overstaffing and understaffing at facilities. If a contract tower is overstaffed by more than 3 percent above the agreed upon staffing plan, without prior approval from the FAA contracting officer, the agency could deny payment to the contractor for the hours worked that exceeded the staffing plan. Similarly, FAA could recoup any payments made to the contractor if a facility were understaffed by 3 or more percent. Third, under the new contract, the contractor must certify that the hours billed under the contract are the actual hours worked during each quarter.
These reports should enable the Contract Tower Program Office to track hours of service provided by the contractor and verify that the contractually specified staffing standards are met. FAA will also be able to adjust payments made to the contractor based on the hours of service provided and billed to FAA. For these procedures to be effective, however, FAA will need to periodically audit the reported data on a more frequent basis and ensure that penalties for noncompliance are clear and strictly enforced.
User Perspectives. We discussed the Contract Tower Program and its proposed expansion with users at contract locations, at proposed locations, and with outside organizations. We found that users at contract locations continue to be supportive of the Contract Tower Program. In general, these users told us that the services they receive from contractors are comparable to FAA-operated towers and that they were satisfied with the overall quality and safety of contract operations. Based on their experiences with the Contract Tower Program, these users felt that expanding the Program to other FAA VFR towers would be feasible. At proposed locations, most users were concerned only that the level of service they receive would remain the same if their towers were converted to contract operations.
However, other users were strictly opposed to expanding the Program. For example, one airport director told us that he used the fact that his tower was operated by the FAA as a marketing tool to attract foreign air carriers and encourage commercial service. Other groups, such as the National Air Traffic Controllers Association (NATCA), oppose expanding the Program. NATCA believes that expanding the Program to busier FAA VFR towers would represent a serious departure from the existing Program because the number and complexity of operations at FAA’s 71 VFR towers are significantly higher than operations at current contract towers.
While 15 of FAA’s 71 VFR towers are busier than towers in the existing Program, the remaining 56 VFR towers have, in our opinion, operations that are comparable to towers in the existing Program. These differences underscore the complexities involved in evaluating the feasibility of expanding the Contract Tower Program. They also underscore the need for FAA to develop specific metrics for analyzing actual results of the Program’s expansion to ensure that system safety and efficiency are not affected.
FAA’s Study of Expanding the Contract Tower Program
FAA completed a draft study of expanding the Contract Tower Program in September 1999, but as of April 2000 had not issued a final report to Congress. In the draft study FAA concluded that no net savings would be realized from further expanding the Program because of an agreement with NATCA that establishes a baseline staffing level of 15,000 FAA controllers.
While the decision to expand the Contract Tower Program is ultimately a policy determination that Congress will have to weigh, FAA’s study did not adequately consider several key factors of the feasibility, costs, and benefits of expanding the Program that should be further analyzed and reported to Congress. These include developing better methodology for considering which towers to convert, and evaluating additional cost savings and other benefits that could be realized from expanding the Program.
I. Better Methodology Is Needed for Considering Which Towers to Convert
FAA narrowly defined the congressional request to evaluate FAA towers "without radar capability." For purposes of its study, FAA defined 41 of the 71 VFR towers as meeting the congressional definition. FAA excluded the remaining 30 towers from the study because those facilities were equipped with a monitoring device known as DBRITE and provided limited instrument flight rule (IFR) services through a letter of agreement (LOA) with a larger radar-equipped facility.
We do not agree that those factors are reasonable causes for including or excluding towers from consideration. For example, there are currently as many as 40 towers in the existing Contract Tower Program that also are equipped with DBRITE displays and provide similar IFR services through LOAs with larger FAA facilities.
We observed operations at 15 of the contract towers with LOAs and compared their operations to 12 of the 30 FAA towers excluded from the study. We concluded that, other than the level of air traffic activity, there were no differences in the nature or types of operations conducted at those facilities.
The methodology FAA used would also result in some lower activity towers being excluded from consideration while busier and larger facilities would be considered for conversion to contract operations. For example, using FAA’s methodology, Ann Arbor Municipal Airport (with an average air traffic count of 43 aircraft per hour) would be excluded from consideration because the facility is equipped with a DBRITE and has an LOA for IFR operations with a larger FAA facility. In contrast, Pontiac/Oakland International Airport (with an average air traffic count of 76 aircraft per hour) would be considered for conversion because the facility is not equipped with DBRITE and does not have an LOA for IFR operations with another FAA facility.
Significant Differences Among FAA’s 71 VFR Towers Need to Be Considered. The methodology used by FAA did not adequately consider important differences about the 71 VFR towers. Unlike most towers in the Contract Tower Program which are relatively similar (primarily low activity general aviation airports), FAA’s 71 VFR towers are not a homogeneous group. These facilities have significant differences in the volume of air traffic they control, the number and types of users they serve, and the complexity of the airspace they manage. For example, the average hourly traffic density at the 71 VFR towers ranges from 28 aircraft per hour to over 118 aircraft per hour. One VFR tower, Van Nuys, California, is the fifth busiest air traffic control tower in the country. In all, 11 of the 71 VFR towers are among FAA’s top 50 busiest air traffic control towers in the United States.
The mix and types of users at the 71 locations also vary extensively. For example, many of these towers handle only general aviation aircraft while others have daily commercial jet service. For example, Long Beach, California, has daily domestic service from American and America West Airlines, and Orlando Sanford, Florida, has regularly scheduled international service from Europe.
Finally, the complexity of the airspace controlled varies among the 71 VFR towers. Several towers have relatively simple and open airspace while others must interact extensively with larger and busier airports. For example, Orlando Executive’s airspace lies directly under a major approach and departure path for Orlando International Airport. These factors, at a minimum, should be included in any criteria used to determine which facilities should or should not be considered for conversion to contract operations.
FAA ATC Grades Could Provide a Better Means for Evaluating Towers. Although many of the differences between FAA’s 71 VFR towers have already been taken into account under FAA’s reclassification efforts, FAA did not use ATC Grades in determining which towers to consider. In 1998, FAA reclassified all its air traffic control facilities into ATC Grades 3 through 12 based on various factors including the volume of air traffic and complexity of operations at each location.
Under the new system, facilities that were previously rated at the same level may have been reclassified into different ATC Grades. For example, under FAA’s old classification system, air traffic control towers at the Chicago O’Hare and John F. Kennedy airports were classified as Level V facilities, but under the new system the facilities were reclassified as ATC Grades 12 and 10, respectively. As shown in the following table, the 71 VFR towers have been reclassified into ATC Grades 5 through 9.
ATC GRADES OF FAA’s 71 VFR TOWERS
ATC GRADE |
TOWERS |
CONTROLLERS* |
5 |
10 |
110 |
6 |
25 |
301 |
7 |
28 |
372 |
8 |
4 |
75 |
9 |
4 |
101 |
Total |
71 |
959 |
*As of December 1999.
In our opinion, the ATC Grades of the 71 towers offer Congress and FAA a more comprehensive means for evaluating which facilities to consider by taking into account factors such as the volume of air traffic, the types of users, and the complexity of operations at each location. Additionally, should Congress choose to expand the Contract Tower Program, FAA will need to develop specific metrics for analyzing and reporting actual results of the Program’s expansion (on a facility-by-facility basis) to ensure that system safety and efficiency are not affected and that projected benefits are being fully realized.
II. Additional Cost Savings Could be Realized by Expanding the Program
FAA estimates that contracting out its VFR towers could result in average annual savings of approximately $787,000 per facility. FAA’s cost comparison was conducted by averaging the annual costs of 12 facilities with high air traffic density already in the Contract Tower Program with 12 of the 71 FAA facilities with similar density counts. FAA’s methodology was based on a framework using Office of Management and Budget Circular A-76 requirements for cost comparisons. We tested the costs used in FAA’s estimate and found that the underlying data were reasonable.
The estimated savings from expanding the Contract Tower Program could be greater, however. FAA’s estimates were based on using FY 1998 costs. In FY 1999, FAA salary costs increased as a result of a new pay system for FAA controllers, which in turn increased the costs of operating FAA towers.
OIG Estimated Savings. Using FAA’s methodology and actual contract and agency costs for FY 1999, we recalculated the potential savings of expanding the Contract Tower Program. We estimate that annual average savings could be as much as $881,000 per tower, or approximately $62.5 million if all 71 VFR towers were contracted out.
The cost of operating FAA’s 71 towers will increase further as a result of new pay differential for FAA controllers. In November 1999, FAA and NATCA agreed to implement a Controller Incentive Pay for controllers at high-cost-of-living locations. FAA controllers at 30 of the 71 locations began receiving an additional pay differential between 5 and 10 percent in FY 2000.
Contract Costs May Be Higher Than Estimated. Actual contract costs may be higher than the average used in FAA’s estimate for several reasons.
FAA’s Contract Tower Program Office is aware of each of these issues and is making plans to address them should the Contract Tower Program be expanded.
III. Other Benefits Should Be Considered
FAA concluded that there would be no savings realized from expanding the Contract Tower Program because of a July 1998 Memorandum of Agreement between FAA and NATCA. Article I of that agreement establishes a baseline staffing level of 15,000 controllers for FYs 1999 through 2001, increasing by 2 percent in FYs 2002 and 2003. The agreement states:
The agency will backfill in order to maintain these numbers when attrition, transfers, or promotions reduce the staffing below the agreed upon numbers.
As a result, FAA concluded that there could be no net savings from expanding the Contract Tower Program because the agreement prohibits a decrease in the number of FAA personnel. However, this conclusion is based on only one possible outcome of expanding the Program. FAA should have more adequately considered several other options before arriving at that conclusion.
Other Considerations. While the agreement with NATCA may represent an expression of policy between the agency and union and reflect their objectives, Congress is not bound by its terms. In providing funding to and authorizing the programs and activities of FAA, Congress may exercise its constitutional prerogative by modifying the provisions or the underlying assumptions of the agreement.
Other Benefits. More importantly, other long-term benefits would accrue from expanding the Program regardless of the agreement with NATCA. Controllers from contracted towers could have a significant impact in meeting projected increases in air traffic demand. As shown in the following graph, FAA is forecasting aircraft operations at airports with FAA-operated air traffic services to increase from about 54 million operations in 2000 to over 67 million operations in 2010 – an increase of over 24 percent.
Forecast Aircraft Operations at Airports with FAA-Operated Air Traffic Services
FAA's study should have given greater merit to the potential impact that controllers from contracted VFR towers could have in offsetting potential future increases in system demands. Contracting out additional VFR tower operations would allow the agency to redistribute controllers (or their equivalent full-time positions) from contract locations to FAA locations with the greatest forecast increases.
Reassigning controllers from the 71 facilities would also reduce FAA’s projected hiring needs thus reducing costs associated with training newly hired controllers. FAA spends approximately $47,000 per employee to provide newly hired controllers initial air traffic control training. According to FAA officials, the agency is planning to hire over 2,000 new controllers over the next 4 years.
Experienced FAA controllers from contracted locations could also help alleviate existing staffing deficiencies. For example, as of December 1999, the Los Angeles International Airport tower was understaffed by eight controllers. If the Program were expanded, the 13 controllers assigned to the Santa Monica tower (or their equivalent full-time positions) could be reassigned to Los Angeles International and address that facility’s staffing needs. Actions such as these would also help FAA reduce overtime expenditures at understaffed facilities. In FY 1999, FAA incurred over $19 million in overtime costs to meet operational needs.
FAA should more carefully examine the potential benefits that expanding the Contract Tower Program could provide in addressing existing staffing deficiencies and ensuring that FAA has sufficient resources at key locations to meet projected increases in demand.
Recommendations
We recommend that FAA:
71 VFR Towers Considered in FAA's Report to
Congress on the Contract Tower Program
ATC Grade 5 VFR Towers |
||||||
State |
Airport |
Density As of 11/99, unless noted |
Staffing As of 12/31/99 |
Excluded in FAA’s Study |
Controller Incentive Pay |
|
AK |
Juneau International |
39.98 |
10 |
No |
0.0% |
|
AZ |
Grand Canyon Municipal |
56.59 |
10 |
No |
0.0% |
|
CA |
El Monte |
36.23 |
10 |
No |
8.0% |
|
CA |
Napa County |
42.19 |
11 |
No |
5.5% |
|
CA |
Santa Rosa Sonoma |
35.88 |
12 |
No |
5.5% |
|
FL |
Fort Pierce |
38.14 |
13 |
No |
0.0% |
|
IN |
Lafayette/Perdue University |
45.29 |
11 |
No |
0.0% |
|
MI |
Ann Arbor Municipal |
43.10 |
12 |
Yes |
5.0% |
|
MI |
Traverse City |
35.55 (10/99) |
9 |
No |
0.0% |
|
VA |
Manassas Regional/Davis Field |
27.89 |
12 |
No |
5.5% |
|
ATC-5 Staffing |
110 |
|||||
ATC Grade 6 VFR Towers |
||||||
AZ |
Scottsdale |
48.55 |
14 |
No |
0.0% |
|
CA |
Camarillo |
45.33 |
11 |
No |
8.0% |
|
CA |
Concord/Buchanan Field |
52.50 |
9 |
No |
8.0% |
|
CA |
Hayward Air Terminal |
45.65 |
11 |
No |
8.0% |
|
CA |
Livermore Municipal |
60.30 |
10 |
No |
8.0% |
|
CA |
Sacramento International |
31.70 |
15 |
Yes |
0.0% |
|
CA |
San Jose/Reid-Hillview |
48.56 |
9 |
No |
8.0% |
|
CO |
Denver/Jeffco |
38.32 |
15 |
No |
0.0% |
|
DE |
Wilmington/New Castle |
33.06 |
12 |
No |
0.0% |
|
FL |
Miami/Kendall-Tamiami |
47.30 |
13 |
Yes |
0.0% |
|
FL |
Vero Beach |
50.98 |
14 |
No |
0.0% |
|
IL |
Cahokia/St. Louis |
49.22 |
12 |
Yes |
0.0% |
|
IL |
Chicago/Aurora Municipal |
33.74 |
13 |
No |
5.5% |
|
KY |
Louisville Bowman |
38.29 |
11 |
Yes |
0.0% |
|
LA |
New Orleans/Lakefront |
40.91 |
11 |
Yes |
0.0% |
|
MI |
Detroit Willow Run |
37.28 (10/ 99) |
12 |
Yes |
4.5% |
|
MN |
Minneapolis/Crystal |
48.51 |
11 |
Yes |
0.0% |
|
MN |
St. Paul Downtown |
39.61 |
12 |
No |
0.0% |
|
MO |
Spirit of St. Louis |
47.19 |
14 |
Yes |
0.0% |
|
NY |
Poughkeepsie/Dutchess |
33.43 |
8 |
No |
0.0% |
|
OR |
Portland-Hillsboro |
55.94 |
10 |
No |
0.0% |
|
PA |
Northeast Philadelphia |
48.86 |
12 |
No |
5.5% |
|
PA |
Pittsburgh/Allegheny County |
28.33 |
14 |
Yes |
0.0% |
|
TX |
Fort Worth/Alliance |
49.78 |
17 |
Yes |
0.0% |
|
WA |
Everett Paine Field |
57.75 |
11 |
No |
0.0% |
|
ATC-6 Staffing |
301 |
|||||
ATC Grade 7 VFR Towers |
|||||
State |
Airport |
Density As of 11/99, unless noted |
Staffing As of 12/31/99 |
Excluded in FAA’s Study |
Controller Incentive Pay |
AK |
Anchorage/Merril Field |
49.36 |
12 |
No |
0.0% |
AZ |
Mesa/Falcon Field |
56.67 |
13 |
No |
0.0% |
AZ |
Phoenix-Deer Valley Municipal |
63.74 |
15 |
No |
0.0% |
AZ |
Prescott/EA Love Field |
89.72 |
18 |
No |
0.0% |
CA |
Carlsbad/McClellan |
62.55 |
14 |
No |
5.5% |
CA |
Chino |
44.56 |
10 |
No |
4.5% |
CA |
La Verne/Bracket Field |
59.97 |
11 |
No |
8.0% |
CA |
Palo Alto |
47.99 |
10 |
No |
8.0% |
CA |
San Diego/Gillespie Field |
49.46 |
12 |
No |
5.5% |
CA |
San Diego/Montgomery |
58.04 |
16 |
No |
5.5% |
CA |
Santa Monica Municipal |
53.44 |
13 |
Yes |
8.0% |
CA |
Torrance/Zamperini Field |
51.55 |
10 |
No |
8.0% |
FL |
Fort Lauderdale Executive |
48.66 (9/99) |
15 |
Yes |
0.0% |
FL |
Orlando Executive |
45.17 |
11 |
Yes |
0.0% |
GA |
Atlanta/Dekalb-Peachtree |
50.52 |
16 |
Yes |
0.0% |
IL |
Chicago/Du Page |
46.57 (10/99) |
16 |
Yes |
5.5% |
IL |
Chicago/Palwaukee Municipal |
38.36 |
14 |
Yes |
5.5% |
MA |
Bedford/Hanscom Field |
46.45 |
13 |
Yes |
8.0% |
MA |
Nantucket Memorial |
39.75 |
9 |
Yes |
8.0% |
MN |
Minneapolis/Flying Cloud |
50.42 |
14 |
No |
0.0% |
ND |
Grand Forks International |
57.26 |
16 |
Yes |
0.0% |
NJ |
Caldwell/Essex County |
56.52 |
13 |
No |
5.5% |
NJ |
Morristown Municipal |
56.99 |
11 |
No |
5.5% |
NV |
North Las Vegas |
51.55 |
17 |
Yes |
0.0% |
NY |
Farmingdale/Republic |
57.75 |
12 |
No |
8.0% |
TX |
Dallas Addison |
36.48 |
15 |
Yes |
0.0% |
TX |
Tomaball D. W. Hooks |
62.02 |
13 |
Yes |
0.0% |
VA |
Newport News |
48.28 |
13 |
No |
0.0% |
ATC-7 Staffing |
372 |
||||
ATC Grade 8 VFR Towers |
|||||
FL |
Orlando/Sanford |
78.11 |
18 |
Yes |
0.0% |
MI |
Pontiac/Oakland Ct'y Internat'l |
76.22 (6/99) |
17 |
No |
5.5% |
OK |
Tulsa/Riverside |
70.77 |
17 |
Yes |
0.0% |
WA |
Seattle/Boeing Field |
72.68 |
23 |
Yes |
5.5% |
ATC-8 Staffing |
75 |
||||
ATC Grade 9 VFR Towers |
|||||
CA |
Long Beach/Daughtery |
97.80 |
29 |
Yes |
8.0% |
CA |
Van Nuys |
118.35 |
23 |
Yes |
8.0% |
CO |
Denver/Centennial |
97.45 |
24 |
Yes |
0.0% |
TX |
Fort Worth Meacham |
75.97 |
25 |
Yes |
0.0% |
ATC-9 Staffing |
101 |
||||
Total Staffing |
959 |
Scope and Methodology
This review was conducted between October 1999 and February 2000. Exhibit D lists the activities we visited or contacted during the audit. We conducted the audit in accordance with Government Auditing Standards prescribed by the Comptroller General of the United States and included such tests as we considered necessary to provide reasonable assurance of detecting abuse or illegal acts. Our methodology was designed around answering the following four questions.
Were previously identified staffing problems in the Federal Contract Tower Program corrected? To address this question, we conducted a follow-up review of staffing issues noted in our 1998 audit. We selected a judgmental sample of 37 towers and reviewed a sample of controller payroll records for approximately 4 biweekly pay periods (2 months) in 1999. We then compared the number of controllers and hours provided to staffing requirements. We also reviewed the new contract solicitation to assess FAA’s procedures for oversight of contractor compliance. In addition, we reviewed a sample of the most recent facility evaluation reports conducted by FAA’s Evaluations Branch.
Is FAA’s claim that towers with a DBRITE and an LOA for IFR operations cannot be contracted a valid assertion? To address this question, we selected and visited a total of 27 towers (12 of the 71 FAA VFR towers and 15 contract towers). At these towers, two members of our staff (former air traffic controllers) observed air traffic operations to determine if there was a discernible difference in operations justifying excluding certain FAA towers from contract consideration. In addition, we interviewed airport management officials and users to determine if services received at contract towers are comparable to FAA-operated towers.
Were all costs and estimates used in FAA’s study reasonable? To address this question, we reviewed the methodology FAA used for estimating the average annual savings. We compared FAA’s methodology to Office of Management and Budget Circular A-76 requirements for cost comparisons. We also traced to source documents a sample of the costs used by FAA to determine if the underlying data were accurate. Using FY 1999 cost data and FAA’s methodology, we calculated the potential average cost savings for the contract towers and FAA-operated towers.
What other costs and benefits should have been considered in FAA’s study? To address this question, we reviewed FAA’s FYs 1999 and 2000 budget requests to identify other cost factors that would be impacted by expanding the Contract Tower Program. These include projected increases in air traffic activity, overtime costs, training costs for new controllers, and average relocation costs. We also interviewed FAA officials responsible for training, staffing, and hiring.
Comparison of Potential Cost Savings for FY 1998 and FY 1999
FY 1998 Cost Comparison |
FY 1999 Cost Comparison |
|||||||||||||||
FAA Facility |
FY 98 Cost |
FCT Facility |
FY98 Cost |
FAA Facility |
FY99 Cost |
FCT Facility |
FY99 Cost |
|||||||||
Concord, CA |
$1,353,338 |
Anoka, MN |
$423,456 |
Concord, CA |
$1,320,939 |
Anoka, MN |
$427,152 |
|||||||||
Everett, WA |
$1,047,324 |
Carbondale, IL |
$299,784 |
Everett, WA |
$1,023,432 |
Carbondale, IL |
$305,064 |
|||||||||
Fort Pierce, FL |
$1,113,654 |
Chandler, AZ |
$392,550 |
Fort Pierce, FL |
$1,255,938 |
Chandler, AZ |
$431,460 |
|||||||||
Hillsboro, OR |
$1,098,362 |
Gateway, AZ |
$368,696 |
Hillsboro, OR |
$1,225,717 |
Gateway, AZ |
$380,064 |
|||||||||
Juneau, AK |
$1,066,483 |
Gwinnett, GA |
$297,108 |
Juneau, AK |
$1,008,362 |
Gwinnett, GA |
$316,008 |
|||||||||
Lafayette, IN |
$1,212,747 |
Hollywood, FL |
$307,872 |
Lafayette, IN |
$1,130,407 |
Hollywood, FL |
$314,376 |
|||||||||
Livermore, CA |
$1,236,710 |
Lakeland, FL |
$382,908 |
Livermore, CA |
$1,458,186 |
Lakeland, FL |
$384,000 |
|||||||||
Manassas, VA |
$917,365 |
Norman, OK |
$273,509 |
Manassas, VA |
$1,211,751 |
Norman, OK |
$273,509 |
|||||||||
Napa, CA |
$1,037,942 |
Pompano Beach, FL |
$267,420 |
Napa, CA |
$1,221,485 |
Pompano Beach, FL |
$284,364 |
|||||||||
Santa Rosa, CA |
$1,097,095 |
Ryan Field, AZ |
$350,016 |
Santa Rosa, CA |
$1,251,043 |
Ryan Field, AZ |
$377,916 |
|||||||||
Traverse City, MI |
$931,663 |
San Carlos, CA |
$345,228 |
Traverse City, MI |
$1,055,801 |
San Carlos, CA |
$345,228 |
|||||||||
Vero Beach, FL |
$1,335,207 |
Stewart, NY |
$301,692 |
Vero Beach, FL |
$1,671,332 |
Stewart, NY |
$424,860 |
|||||||||
$13,447,890 |
$4,010,239 |
$14,834,393 |
$4,264,001 |
|||||||||||||
Average FAA VFR Tower = $1,120,658 |
Average FAA VFR Tower = $1,236,199 |
|||||||||||||||
Average Contract Tower = $334,187 |
Average Contract Tower = $355,333 |
|||||||||||||||
Average Savings = $786,471 |
Average Savings = $880,866 |
|||||||||||||||
Total Cost Savings for 71 Towers = $55,839,441 |
Total Cost Savings for 71 Towers = $62,541,486 |
|||||||||||||||
The cost comparison was conducted by averaging the annual cost of 12 high-density facilities already in the Contract Tower Program (FCT Facilities) and averaging the annual cost of 12 FAA towers with similar densities that qualified to be contracted out under FAA's draft report to Congress for both FY 1998 and FY 1999. |
Activities Visited or Contacted
FAA Air Traffic Control Towers
Facility State
Long Beach CA
Santa Monica CA
Torrance CA
Van Nuys CA
Fort Lauderdale Executive FL
Orlando Executive FL
Orlando Sanford FL
Tamiami FL
Dallas/Addison TX
Fort Worth/Alliance TX
Fort Worth/Meacham TX
Seattle Boeing WA
Federal Contract Towers (FCT)
Facility State Contractor
Topeka/Forbes Field KS Midwest
Johnson County Executive KS Midwest
Melbourne FL RVA
Naples Municipal FL RVA
Opa Locka FL RVA
Page Field FL RVA
Brownsville TX RVA
Dallas/Redbird TX RVA
Harlingen TX RVA
McAllen TX RVA
Fullerton CA Serco
Palmdale CA Serco
San Diego/Brown Field CA Serco
Renton WA Serco
Seattle/Tacoma Narrows WA Serco
FCT Contractors
Midwest Air Traffic Control Services, Olathe, KS
Robinson-VanVuren Associates, Oklahoma City, OK
Serco Management Services, Palmdale, CA
Activities Visited or Contacted (Continued)
Aviation Associations
Executive Vice President, American Association of Airport Executives, Alexandria, VA
Representatives of National Air Traffic Controllers Association
Users
California
Commander, United States Air Force, Palmdale
Airport Manager, San Diego, Brownfield
Airport Manager, Assistant Airport Manager, and Superintendent, Van Nuys Airport
Airport Noise Operations Technician, City of Santa Monica Airport Authority
Airport Operations Analyst, Long Beach
Representative, Boeing Corporation, Long Beach
Florida
Manager, General Aviation, Page Field General Aviation Airport
Manager, Government Affairs, Southwest Florida International Airport
Department Director, General Aviation/Facilities, Southwest Florida International Airport
Airport Manager, Tamiami Airport
Chief of Safety, Miami Dade County
Executive Director, City of Naples Airport Authority
Assistant Airport Manager, Fort Lauderdale Executive Airport
Representatives of World Jet, Incorporated, Fort Lauderdale
Representatives of Aero Design, Fort Lauderdale
Manager, Opa Locka Airport
Executive Director, Orlando Sanford Airport Authority
Director of Operations and Maintenance, Orlando Sanford Airport Authority
Director of General Aviation, Melbourne International Airport
Airport Operations Manager, Melbourne International Airport
Chief of Police, Melbourne Airport Police Department
Chief Flight Engineer, Surveillance & Battle Management Systems, Northrop Grumman, Melbourne
Director of Operations, Florida Institute of Technology, Melbourne
Representatives of Atlantic Jet Center, Melbourne
Kansas
President, Metro Topeka Airport Authority
Activities Visited or Contacted (Continued)
Washington
Airport Manager, Comarco Airport Services, Tacoma Narrow
Airport Manager, Renton Municipal Airport
Airport Manager, King County International Airport, Boeing Field
Senior Engineer, Boeing Corporation, Seattle
Texas
Airport Manager, City of Fort Worth Aviation Department, Meacham Airport
President, Alliance Air/Aviation Services
President, Addison Airport of Texas, Inc.
Assistant Airport Manager, Redbird Airport Management
Director and Assistant Director of Aviation, Valley International Airport
Assistant Director of Aviation, City of Brownsville Department of Aviation
Director of Aviation, City of McAllen Department of Aviation